With breakup in full swing, ALMR is gearing up for a busy spring and summer season!

Staff from the System Management Office and Motorola technicians will be making their way around the state installing the GTR upgrades. Each site being upgraded will be completely down for 6-8 hours. Watch the ALMR Daily System Status for updates.

Completed and Upcoming:

  • Pipeline Hills 4/28/21 (COMPLETED)
  • Ski Hill   4/29/21 (COMPLETED)
  • Nikiski    4/30/21 (COMPLETED)
  • Kassilof  5/1/21 (COMPLETED)
  • Ninilchik  5/2/21 (COMPLETED)
  • Whittier 5/5/21 (COMPLETED
  • Seward 5/10/21 (COMPLETED)
  • Moose Pass 5/12/21 (COMPLETED)
  • Portage 5/14/21 (COMPLETED)
  • Diamond Ridge 5/18/21 (COMPLETED)
  • Anchor River 5/19/21 (COMPLETED)
  • Sterling 5/20/21 (COMPLETED)
  • Kenai 5/21/21 (COMPLETED) 
  • Paxon TBD
  • Girdwood TBD

The Quantar/GTR Replacement project kicked off last July and 16 sites were upgraded. The goal for this year is to upgrade 50 sites!